Job PO # | 226075 | SCS Job # | J-20-28008 |
Sales Engineeer | Josh Huffman | 406-585-7333 | Project Admin | Z - Liz Pullman | 406-551-7221 |
Updated | 11/23/2022 1:56 pm |
PO | Shipping | Delivery | ||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
SCS PO# | MANUFACTURER | TAG | LINE | DESCRIPTION | ORD | SHIP | DELV | B/O | STATUS | ORIGINAL ESTIMATED SHIP DATE | REVISED ESTIMATED SHIP DATE | ACTUAL SHIP DATE | TRACKING | NOTES | ESTIMATED DELIVERY DATE | ACTUAL DELIVERY DATE | SIGNED | NOTES |
20-28008-01 | Mason Industries | Line 1 | Lot of Mason Industries Seismic | 1 | 1 | 1 | 0 | DELIVERED | 03/12/2021 | 02/23/2021 | 03/01/2021 | 03/01/2021 | BROERMAN | |||||
20-28008-02 | Ferguson | DWH-1, DWH-2 | Line 1 | BTH-150(A) | 2 | 2 | 2 | 0 | DELIVERED | 01/13/2021 | 12/21/2020 | 12/21/2020 | OLD DOMINION | 12/28/2020 | 12/28/2020 | Steve | ||
20-28008-03 | Keller Supply | AS-1 | Line 1 | 4-IN-1 Hydraulic Separator
| 1 | 1 | 1 | 0 | DELIVERED | 02/17/2021 | 02/05/2021 | 02/05/2021 | 02/12/2021 | 02/12/2021 | Broerman | |||
HDP-1, HDP-2, BCP-1, BCP-2 | Line 2 | MAGNA1 40-120F
| 2 | 0 | 0 | 0 | ORDERED | |||||||||||
CP-1 | Line 3 | Domestic Circulator Pump
| 1 | 0 | 0 | 0 | ORDERED | |||||||||||
20-28008-04 | TM Sales Inc. - Meek Brothers | Line 1 | Axiom
Tag: GF-1
MF-300 Glycol Feeder
17 Gallon Storage Capacity
RIA10-1SAA Alarm Panel | 1 | 1 | 1 | 0 | DELIVERED | 02/11/2021 | 02/04/2021 | 02/04/2021 | 02/04/2021 | Broerman | |||||
20-28008-05 | Armstrong Pumps | Line 1 | Armstrong
Tag: ET-1
A200-L Bladder Type Expansion Tank
ASME Rated | 1 | 1 | 1 | 0 | DELIVERED | 03/17/2021 | 02/24/2021 | 02/24/2021 | OTHER 20832323 CMF | 03/03/2021 | 03/03/2021 | STEVE | |||
Line 2 | Armstrong
Tag: TEA-1
AST-30 Diaphragm Type Expansion Tank (Potable Water)
ASME Rated | 1 | 1 | 1 | 0 | DELIVERED | ||||||||||||
20-28008-06 | BKI Industries | Line 1 | Condensate Neutralizer Kit BKI-1000 | 1 | 0 | 0 | 0 | DELIVERED | 02/03/2021 | 02/08/2021 | 02/08/2021 | Broerman | ||||||
20-28008-07 | RIELLO | B-1, B-2 | Line 1 | Condexa Pro 117 Wall Hung Boiler | 2 | 2 | 2 | 0 | DELIVERED | 02/17/2021 | 02/10/2021 | OTHER P286718 Ontario New England Express | 02/22/2021 | 02/22/2021 | n/a | |||
Line 2 | Sensor for Primary Loop | 2 | 0 | 0 | 0 | SHIPPED | ||||||||||||
Line 3 | BACnet Gateway (RS485) | 1 | 0 | 0 | 0 | SHIPPED | ||||||||||||
Line 4 | Outdoor Sensor for Condexa Pro | 1 | 0 | 0 | 0 | SHIPPED | ||||||||||||
Line 5 | 1 | 0 | 0 | 0 | SHIPPED | |||||||||||||
20-28008-08 | Mason Industries | Line 1 | Lot of Mason Industries Seismic Isolation | 1 | 0 | 0 | 0 | SHIPPED | 03/26/2021 | 03/09/2021 | 03/15/2021 | |||||||
20-28008-09 | S. Conley Support | Line 1 | Startup | 1 | 0 | 0 | 0 | SHIPPED | 06/17/2021 | 07/14/2021 | ||||||||
20-28008-10 | S. Conley Support | Line 1 | SO# 22-61823
Boiler inspection and combustion analysis on 6/7/22 | 1 | 0 | 0 | 0 | ORDERED |