Job PO # | 318583 | SCS Job # | J-20-24504 |
Contractor | Temp Right Service | ||
Sales Engineeer | Sean Mattick | 406-585-7333, Ext 3011 | Project Admin | Liz Pullman | 406-551-7221 |
Updated | 09/28/2020 1:24 am |
Release | Shipping | Delivery | Freight Claims | |||||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
SCS PO# | MANUFACTURER | TAG | DESCRIPTION | # ORDERED | # DELIVERED | # B/O | STATUS | RELEASE | ORDERED | LEAD | NOTES | ESTIMATED | ACTUAL | TRACKING | NOTES | ESTIMATED | ACTUAL | SIGNED | NOTES | ISSUES | CLAIM # | NOTES |
PO-20-24504-01 | West Coast - Omniduct | Lot Low Pressure Single Wall Galvanized Spiral Pipe and Fittings with Couplers Every 10' | 1 | 1 | 0 | DELIVERED | 02/13/2020 | 02/13/2020 | 3-5 days | 02/14/2020 | 02/14/2020 | Old Dominion NA | 02/21/2020 | 02/21/2020 | ||||||||
PO-20-24504-02 | Flexmaster | Lot Low Pressure Insulated R6.0 Flex Duct | 1 | 1 | 0 | DELIVERED | 02/13/2020 | 02/13/2020 | 2-3 weeks | 02/21/2020 | 02/20/2020 | FedEx 120374204473 | AAldridge | 02/25/2020 | 02/25/2020 | |||||||
High Efficiency Take Offs w/out Dampers | 2 | 2 | 0 | DELIVERED | 02/13/2020 | 02/13/2020 | 02/21/2020 | 02/20/2020 | FedEx 120374204473 | AAldridge | 02/25/2020 | 02/25/2020 | ||||||||||
High Efficiency Take Offs w/out Dampers | 1 | 1 | 0 | DELIVERED | 02/13/2020 | 02/13/2020 | 02/21/2020 | 02/20/2020 | FedEx 120374204473 | AAldridge | 02/25/2020 | 02/25/2020 | ||||||||||
PO-20-24504-03 | Nailor Industries | Manual Operated Volume Dampers w/ Hand Locking Quadrants and 2" Standoffs | 13 | 13 | 0 | DELIVERED | 02/13/2020 | 02/13/2020 | 3-4 weeks | 03/06/2020 | 03/09/2020 | FedEx 165153527820 | 03/12/2020 | 03/12/2020 | DDavis | |||||||
PO-20-24504-04 | Keller Supply | Lot 4" Aluminum Dryer Venting | 1 | 1 | 0 | DELIVERED | 02/13/2020 | 02/13/2020 | NA | 02/13/2020 | 02/13/2020 | UPS NA | 02/17/2020 | 02/17/2020 | NA | |||||||
PO-20-24504-05 | Johnson Controls | JCI Model J03ZEH05 Packaged Rooftop Unit
- Hinged Access Panels
- Single Point Power Connection
- Hail Guards
- Powered Convenience Outlet
- Extra Set of Filters
- Curb Adapter
- Disconnect
- Unit Controller
- Thermostat
TAG: RTU-48
* Excludes Factory Authorized Startup | 1 | 1 | 0 | DELIVERED | 02/14/2020 | 02/14/2020 | 03/09/2020 | 03/23/2020 | OTHER NA | 03/23/2020 | 03/23/2020 | NA | ||||||||
PO-20-24504-06 | Renew Aire | RenewAire Model HE1XRTV Energy Recovery Ventilator
- Factory Mounted Disconnect and Relay
- Roof Curb
- Motorized Dampers for Both Airstreams
TAG: ERV-48 | 1 | 1 | 0 | DELIVERED | 02/14/2020 | 02/14/2020 | 3-4 weeks | 03/12/2020 | 03/12/2020 | UPS NA | 03/19/2020 | 03/19/2020 | NA | |||||||
RenewAire Model EK-1212 Electric Duct Heating Coil
- Disconnect
- Control Panel
- SCR Control
TAG: EDC-48 | 1 | 1 | 0 | DELIVERED | 02/14/2020 | 02/14/2020 | 03/12/2020 | 03/12/2020 | UPS NA | 03/19/2020 | 03/19/2020 | NA | ||||||||||
PO-20-24504-07 | Nailor Industries | Grilles, Registers and Diffusers | 19 | 19 | 0 | DELIVERED | 02/17/2020 | 02/17/2020 | 03/27/2020 | 04/01/2020 | XPO 252068865 | 04/08/2020 | 04/08/2020 | Willis | ||||||||
PO-20-24504-08 | Thybar Corporation | Curb Adapter | 1 | 1 | 0 | DELIVERED | 02/17/2020 | 02/17/2020 | 3-5 days | 02/20/2020 | 02/19/2020 | SAIA 10356138520 | 02/24/2020 | 02/24/2020 | NA | |||||||
PO-20-24504-09 | Keller Supply | Thermostat | 1 | 1 | 0 | DELIVERED | 02/17/2020 | 02/17/2020 | 4-5 weeks | 03/17/2020 | 03/17/2020 | OTHER NA | 03/24/2020 | 03/24/2020 | NA | |||||||
1 | 0 | 0 | 02/17/2020 | 02/17/2020 | 03/17/2020 | 03/17/2020 | OTHER NA | 03/24/2020 | 03/24/2020 | NA |